Prime Energy has brought the Malampaya Phase 4 wells onstream, adding about 222 Bcf of recoverable gas from two deepwater wells offshore Palawan. First gas flowed to the Batangas onshore plant on 5 Nov 2026, 27 months after final investment decision. Output is set to ramp up over the coming months.

Philippines Midstream/Pipelines Commissioning gas processing plant Owner: Prime Reported · 16 sources Latest news: 6 Nov 2026

Map

Map of Offshore Palawan (Camago and Malampaya East fields), with gas processed at the Malampaya Onshore Gas Plant, Batangas City, Philippines, Philippines with a point on the project

Offshore Palawan (Camago and Malampaya East fields), with gas processed at the Malampaya Onshore Gas Plant, Batangas City, Philippines, Philippines.