Projects / P09715
MISO Tranche 2.1 Iowa Transmission Project
Ameren Transmission Company of Illinois
A consortium of Ameren, GridLiance and Dairyland will build about 187 miles of 765-kV line across Iowa, with a new East Adair substation. MISO selected it on 22 Oct 2026, and Ameren and GridLiance lead development. The 345-kV parts are due in service on 1 Jun 2032, the 765-kV line on 1 Jun 2034.
United States
Power – Grid & Storage
Awarded
transmission line Owner: Ameren Transmission Company of Illinois Reported · 2 sources
Latest news: 22 Oct 2026
Map
Southern to northern Iowa, from the East Adair substation to the Minnesota/Iowa state line, Iowa, United States, United States.