Chimuara–Nacala Transmission Line (LTEC), Phases 2 and 3

Gridworks

Gridworks and Electricidade de Moçambique are procuring a turnkey EPC contract for about 460 km of transmission lines in central and northern Mozambique. The package covers one 400 kV line, two 220 kV lines and new substations, and the developers invited expressions of interest on 13 October 2026. Responses are due before 24 November 2026.

Mozambique Power – Grid & Storage Tender transmission line Owner: Gridworks Reported · 1 source Latest news: 13 Oct 2026

Map

Map of Mozambique with a point on the project

Mozambique, whole country: no exact coordinate in the sources.