Global Project Book

Projects / P06731

Princess Elisabeth Energy Island

Elia Transmission Belgium · 3,500 MW · 45 km off the Belgian coast, North Sea, Belgium

Elia Group is building Princess Elisabeth Energy Island, an artificial island 45 km off the Belgian coast that will connect at least 2.1 GW of offshore wind. All 23 caissons are installed, and sand reclamation inside the ring is next. Cable connections to the mainland follow in 2027 and 2028, with completion planned for 2031.

Belgium Power – Grid & Storage Construction substation Owner: Elia Transmission Belgium Reported · 1 source Latest news: 21 Aug 2026

Map

Map of 45 km off the Belgian coast, North Sea, Belgium, Belgium with a point on the project

45 km off the Belgian coast, North Sea, Belgium, Belgium.

More with an account

See the sources behind every fact, the full timeline and who is building it. Free account, no card.