Cero Generation is behind a Larks Green cluster at Itchington, England, that totals 190 MW: 70 MW of solar and two batteries of 50 MW and 70 MW. NORD/LB, Santander, Rabobank and ING closed financing on 23 Jul 2026. The 70 MW Lower Larks battery is under construction, with operation expected in 2027.
United Kingdom
Power – Renewables
Construction
solar PV Owner: Cero Reported · 2 sources
Latest news: 23 Jul 2026