Projects / P04856
NTPC Lara Super Thermal Power Project Stage III
NTPC · 1,600 MW · Lara, Raigarh, Chhattisgarh, India
The NTPC board approved the Lara Stage III expansion on 11 July 2026 at INR 20,456.70 crore, adding two ultra-supercritical 800 MW units in Chhattisgarh. L&T Energy CarbonLite Solutions received a Limited Notice to Proceed for the main plant package. The full notice follows environmental clearance.
Map
Lara, Raigarh, Chhattisgarh, India, India.