Projects / P04195
Transpower Cook Strait HVDC Cable Replacement
Transpower
Transpower is replacing the three Cook Strait HVDC cables and adding a fourth, with new termination stations, raising capacity from 1,200 MW to 1,400 MW. The Commerce Commission approved about NZ$1.1 billion for stage one on 18 June 2026. Construction is due to finish in the early 2030s.
New Zealand
Power – Grid & Storage
FID
transmission line Owner: Transpower Reported · 1 source
Latest news: 30 Jun 2026
Map
New Zealand, whole country: no exact coordinate in the sources.